🏢 Key Departments & Contacts

🔍
Planning & Survey Department

Building permits, plot plans, NOCs, and urban planning approvals

📞 +971-2-417-7777
📧 planning@adm.gov.ae
🏢 Ground Floor, ADM Building
⏰ Sun-Thu: 7:30 AM - 2:30 PM
Building Control Department

Construction permits, structural approvals, and building inspections

📞 +971-2-417-8888
📧 building@adm.gov.ae
🏢 1st Floor, ADM Building
⏰ Sun-Thu: 7:30 AM - 2:30 PM
Environment & Health Department

Environmental clearances, health permits, and safety approvals

📞 +971-2-417-9999
📧 environment@adm.gov.ae
🏢 2nd Floor, ADM Building
⏰ Sun-Thu: 7:30 AM - 2:30 PM
Roads & Infrastructure

Road access permits, infrastructure connections, and traffic approvals

📞 +971-2-417-6666
📧 roads@adm.gov.ae
🏢 Ground Floor, Infrastructure Wing
⏰ Sun-Thu: 7:30 AM - 2:30 PM
Engineering Services

Technical reviews, engineering approvals, and consultant registrations

📞 +971-2-417-5555
📧 engineering@adm.gov.ae
🏢 3rd Floor, Technical Block
⏰ Sun-Thu: 7:30 AM - 2:30 PM
Economic Development

Commercial licenses, business permits, and economic zone approvals

📞 +971-2-417-4444
📧 economic@adm.gov.ae
🏢 4th Floor, Commercial Wing
⏰ Sun-Thu: 7:30 AM - 2:30 PM

💰 Fee Structure 2024

Service Fee (AED) Processing Time Required Documents
Building Permit (Villa) 5,000 - 15,000 21 working days Plans, NOCs, Site Plan
Building Permit (Commercial) 10,000 - 50,000 30 working days Detailed Plans, MEP, Structural
Demolition Permit 2,000 - 8,000 7 working days Site Plan, Safety Plan
Completion Certificate 3,000 - 12,000 14 working days Final Inspections, As-Built
Amendment/Revision 1,000 - 5,000 14 working days Revised Plans, Justification
Extension Request 500 - 2,000 7 working days Progress Report, New Timeline

📋 Approval Process Timeline

1

Initial Submission

Day 1-3: Submit complete application with all required documents through ADM portal or in person. Receive acknowledgment receipt with reference number.

2

Document Review

Day 4-7: Initial document completeness check. Any missing documents will be communicated via SMS/email.

3

Technical Review

Day 8-18: Technical departments review plans for compliance with building codes, zoning, and safety requirements.

4

External Approvals

Day 19-25: Coordination with ADWEA, AADC, and other external authorities for utility and service approvals.

5

Final Approval & Permit Issuance

Day 26-30: Final review, permit fee payment, and permit issuance. Collect physical permit from ADM offices.