📋 Objectives for This Stage
- Monitor the submission status and authority review timeline
- Manage and respond to all technical comments from reviewing departments
- Coordinate any required revisions to drawings or supporting documents
- Ensure all permit fees are paid and clearances obtained
- Secure the official Building Permit to proceed with construction
⚙️ Standard Operating Procedure (SOP)
-
Daily Status Monitoring
PRO to check the municipality portal daily for any updates, comments, or status changes.
Details:- Log all status updates in project tracking sheet
- Responsible: PRO
-
Review Comments Management
Upon receiving technical comments, immediately distribute to relevant team members and schedule a response strategy meeting.
Details:- Categorize comments by discipline: Architectural, Structural, MEP, Civil Defense
- Responsible: Project Architect
-
Coordinate Revisions
For each comment, assign to appropriate team member and set deadline for response. Prepare revised drawings and supporting documents as required.
Details:- All revisions must be reviewed by Project Architect before resubmission
- Responsible: Design Team & Consultants
-
Resubmission Process
Compile all revised documents and resubmit through the portal with a detailed response letter addressing each comment.
Details:- Include summary of all changes made
- Responsible: PRO
-
Permit Collection
Once approval is confirmed, pay all outstanding fees and collect the official Building Permit from the municipality.
Details:- Verify all permit conditions and validity periods
- Responsible: PRO