📋 Objectives for This Stage
- Prepare a complete set of 'Issued for Construction' (IFC) drawings with all necessary details
- Develop comprehensive technical specifications and material schedules
- Create a competitive tender package for contractor selection
- Assist the client in evaluating contractor proposals and selecting the best bid
- Finalize the construction contract and ensure all parties are aligned on project scope
⚙️ Standard Operating Procedure (SOP)
-
Finalize Construction Drawings
Update all architectural drawings to 'IFC' status, incorporating any changes from the approved permit set.
Details:- Include detailed sections, elevations, and construction details
- Responsible: Design Team
-
Coordinate Final Engineering Drawings
Ensure all structural, MEP, and civil drawings are updated and fully coordinated with architectural plans.
Details:- Conduct final clash detection and resolve conflicts
- Responsible: Project Architect & Engineers
-
Prepare Technical Specifications
Develop comprehensive specifications document covering all materials, finishes, and construction methods.
Details:- Use ACAD-SPEC-001 template as the base document
- Responsible: Project Architect
-
Create Tender Package
Compile all construction documents, specifications, and contract terms into a comprehensive tender package.
Details:- Include detailed scope of work and performance requirements
- Responsible: Project Architect
-
Contractor Selection Process
Issue tender to pre-qualified contractors, manage the bidding process, and assist client with contractor selection.
Details:- Evaluate technical and commercial proposals against project criteria
- Responsible: Project Architect